spyder880(m): 2:10pm On Apr 29, 2024
More of the ongoing decking platform carpentry............

spyder880(m): 2:12pm On Apr 29, 2024
More.........

spyder880(m): 2:13pm On Apr 29, 2024
Still more........

spyder880(m): 2:15pm On Apr 29, 2024
Waiting for more bamboo from our supplier, ........

spyder880(m): 4:55pm On Apr 30, 2024
We bought more wood and bamboo today to for the completion of the decking wooden platform ............

spyder880(m): 4:58pm On Apr 30, 2024
Making more blocks for the next stage after this decking ..............

dongc(m): 8:16am On May 01, 2024
spyder880:
Making more blocks for the next stage after this decking ..............
I am just wondering for this project...what were or are your motivations moulding the blocks than what you have done initially in other projects buying?
Cost?
Good savings?
You have enough time ?....
spyder880(m): 1:20pm On May 01, 2024
dongc:

I am just wondering for this project...what were or are your motivations moulding the blocks than what you have done initially in other projects buying?
Cost?
Good savings?
You have enough time ?....

Space to mold
Steady water supply
Steady presence of my supervisor
Instability of cement and sand prices
And yes, I also have enough time to mold in advance

1 Like

spyder880(m): 1:24pm On May 01, 2024
More work pictures today.........

dongc(m): 6:10pm On May 01, 2024
spyder880:


Space to mold
Steady water supply
Steady presence of my supervisor
Instability of cement and sand prices
And yes, I also have enough time to mold in advance

Thank you
spyder880(m): 6:39pm On May 02, 2024
Work ongoing as at yesterday morning..........

spyder880(m): 6:41pm On May 02, 2024
More

bassdow: 1:22pm On May 03, 2024
spyder880:


Space to mold
Steady water supply
Steady presence of my supervisor
Instability of cement and sand prices
And yes, I also have enough time to mold in advance
you forgot mentioning YOU get to determine QUALITY.

1 Like

spyder880(m): 6:50am On May 10, 2024
More pictures from this decking platform work............

spyder880(m): 6:56am On May 10, 2024
More work.......

spyder880(m): 7:57am On May 10, 2024
Preparing for decking reinforcement...............

spyder880(m): 7:59am On May 10, 2024
More pictures

spyder880(m): 9:06am On May 26, 2024
Iron reinforcement works for this decking.......

spyder880(m): 9:10am On May 26, 2024
Electrical piping works, ready for concrete cast...............

Concrete cast of the staircase.

spyder880(m): 9:15am On May 26, 2024
Then let's cast the beams, the floor.....................

spyder880(m): 9:31am On May 26, 2024
Concrete cast..............

spyder880(m): 6:09am On May 28, 2024
Completed portions of the decking..............

spyder880(m): 6:12am On May 28, 2024
Getting blocks ready for the next stage of this project.................

spyder880(m): 6:25am On May 28, 2024
Let's form the walls of the next floor of this building..........

horlabiyi(m): 7:44am On May 28, 2024
Oga,

Please I need your professional advice on this my project, this building is

64ft
58ft
38ft
34ft

I’m trying to get rough estimates for the square meter to use (Gerrard)

I’ll try to some pics to make you understand me better.

spyder880(m): 11:02am On May 28, 2024
horlabiyi:
Oga,

Please I need your professional advice on this my project, this building is

64ft
58ft
38ft
34ft

I’m trying to get rough estimates for the square meter to use (Gerrard)

I’ll try to some pics to make you understand me better.

Good morning bro, you need a proper measurement for this roofing, but only after the roofing wood works are completed. Any other estimates is just a guess work that might not help you so much. In fact, before you complete this wood work, prices may have moved honor down, this is Nigeria where quotation stays relevant for only hours.

1 Like

spyder880(m): 11:03am On May 28, 2024
Still laying blocks on the decking..........

mekussa(m): 11:14am On May 28, 2024
In addition to what @spyder880 said, the "HEIGHT" and design of the roofing 100% affects the number of square meters and materials you will use
E g 1.
A 300sqm(area) sloping roof with a height of 12 feet will use less materials than one that is 14feet high but the materials will be more than a FLAT roof of same area.The height actually has increased the area to be covered

Eg 2.
If Your roofing is one that has a simple design without many valleys,it will need less materials to make as well as save you a lot of cutoffs compared to one that has plenty valleys and throughs.

Like he said,this kind of estimate is best done AT THE SITE by a professional, preferably by either the roofing sheet company rep or the carpenter that will do the roofing.

3 Likes

spyder880(m): 11:20am On May 28, 2024
mekussa:

In addition to what @spyder880 said, the "HEIGHT" and design of the roofing 100% affects the number of square meters and materials you will use
E g 1.
A 300sqm(area) sloping roof with a height of 12 feet will use less materials than one that is 14feet high but the materials will be more than a FLAT roof of same area.The height actually has increased the area to be covered

Eg 2.
If Your roofing is one that has a simple design without many valleys,it will need less materials to make as well as save you a lot of cutoffs compared to one that has plenty valleys and throughs.

Like he said,this kind of estimate is best done AT THE SITE by a professional, preferably by either the roofing sheet company rep or the carpenter that will do the roofing.

You captured it accurately. Thanks.
horlabiyi(m): 3:34pm On May 28, 2024
spyder880:


Good morning bro, you need a proper measurement for this roofing, but only after the roofing wood works are completed. Any other estimates is just a guess work that might not help you so much. In fact, before you complete this wood work, prices may have moved honor down, this is Nigeria where quotation stays relevant for only hours.
thank you for taking your time to respond. Have a blessed week

2 Likes

ghettochild(m): 10:27pm On May 30, 2024
spyder880:
We bought more wood for the lintels of this house...........
i wanted to read to the recent post but then I am forced to ask a question...when u answered the person who said it was a challenging job n you replied saying the basement foundation took more than budgeted for.
now here is my question.
would it have been cheaper if the basement flat waa filled up with laterite n then the whole ground floor will now have its foundation all together..
now here is what I was gonna say when I got to ur last n recent post
you are doing a great job n have made me love engineering...to the point am considering learning under ur tutelage when I return back home.

2 Likes

ghettochild(m): 10:42pm On May 30, 2024
I'm updated now on ur post.
first I must commend u for this n also updating it.
you have made me take a deep interest in building engineer.
back then after secondary school,
I used to work as a labourer...but I never was interested in it as I wanted to go to the university.. a friend I introduced to it is an engineer now as his parents couldn't afford to send him to school... also he wasn't interested in schooling.
I wished I had followed such path.
well that's life.

1 Like

Reply)

Fashola Stops Building Of New Houses In Lagos

(Go Up)

Sections: How To . 29
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or s on Nairaland.