NewStats: 3,264,700 , 8,184,438 topics. Date: Thursday, 12 June 2025 at 05:54 AM 416s3

6382y

Mozel247's Posts 5z5l6d

Mozel247's Posts

(1) (10) (of 17 pages)

mozel247: 9:44am On Jun 22, 2024
duduade:
Your window has no curtain ni
Girl without a bf spotted. Oya come let us date and marry. Chat me up 0 8 1 3 1 1 0 9 5 9 2
mozel247: 10:31pm On Jul 08, 2022
The law is clear. Don't build without approval and if u do, u will b asked to remove it. And if u refuse, govt will help u and u must pay or go to jail

1 Like

mozel247: 11:35am On May 08, 2022
ogwuche4u:


Honestly I have no electrical problem on my Peugeot. It's serving me well. All I do is routine service and that's all.

It is the converted that has electrical issues

2 Likes

mozel247: 8:37am On Mar 15, 2022
mployer:
So why are they afraid of Ukraine ing NATO, when the chief NATO country is their neighbour?

Access to the Black Sea then to Mediterranean and a base in Pacific ocean where they can have more bases in Europe and middle east

1 Like

mozel247: 3:18pm On May 22, 2020
There is a way u will tell ur mum and advise her to take it calmly in a way there won't be family confrontation. Is better before he killed u one day. Don't ever hide anything from ur mum. Never ever try it.

4 Likes

mozel247: 7:52pm On May 18, 2020
2 after ND, 2 during b.tech, 3 during nysc, 0 during msc. 2 post msc. I tried. Only 3 I dated among them. Others were 1-4 night stands
mozel247: 2:31pm On May 09, 2020
dermmy:
Ivanka should go for test asap

Do u read before u comment. Do u know the meaning of teleworking
mozel247: 1:29pm On Mar 16, 2020
Brain
mozel247: 8:59pm On Mar 15, 2020
Something tells that the next shocking event will be death of Tina or Tayo. One of this will happen and help simi retrace her step
mozel247: 8:46pm On Oct 04, 2019
Plastering work picture

mozel247: 8:43pm On Oct 04, 2019
Plastering and roofing was done in earnest and complete

mozel247: 8:41pm On Oct 04, 2019
Roof beam and coping was done successfully

mozel247: 9:40pm On Jul 12, 2019
Update

OK we are back from the extended break. Work has started in earnest and we moving at a very fast pace. Foundation work on going for the stores

mozel247: 4:41am On Jul 03, 2019
Updates

Coping work commences

mozel247: 4:38am On Jul 03, 2019
Update

Blockworks completed 100% . The ministry is moving to permanent site God willing.

We will proceed with the plaster immediately as we won't b for roofing cuz of time constraints. We will be checking weather report daily to schedule our work

mozel247: 9:44pm On Jun 22, 2019
Anytime I see dead body no matter who d person is. I get emotional. It constantly reminds me that I will b just like that someday. Worst if I visit mug. My God. Life is vanity. And not worth all this stress, greed for wealth and others

26 Likes 1 Share

mozel247: 8:07am On Jun 12, 2019
iamblest:
More from different angles.


Due to lack of experience , I used 6 inch blocks for setting of the foundation instead of 9 inches block.i later found out from the bricklayer that 9 inch was the standard block used in setting foundation of a house even if it's just a bungalow house

That is not true. Of what sense setting with 9" and continue with 6". That is rubbish and professionally not advisable.

1 Like

mozel247: 6:07pm On Jun 10, 2019
Update.

There are some issues to sort out with the drawings. Especially the site layout and the numerous unnecessary car parks.

New layout is ready. This is cost effective than the first

Update.

Site terrain making it difficult to kick start the work. Access to site flooded. The option left is to get another entrance to the site. This was completed today. Borehole drilling on going, few of the shops dug already. Pictures attached

mozel247: 4:00pm On Jun 08, 2019
Update

Here is the link to my other on going project.

https://nairaland.macsoftware.info/5127309/a-z-construction-8-units-standard


Currently mobilising to site and site clearance just completed. Setting out probably will start Monday God willing and work start proper after negotiations of and conditions of contract between me and my client (contractor) completed

Am a freelance builder and not under any strict employment of any organization. U can me for ur next mega project. Even the small pet project as well.

mozel247: 3:02am On Jun 08, 2019
Hi guys. It's ur boy again. I will be putting through the processes and stages of the construction of our next mega project; "Mami market". As usually, I will be silence on the location of the project as well as the clients as I wish to treat these info as previleged.

First and foremost. Lemme introduce myself as well as the project

Name: moses

Qualifications: ND building technology Auchi poly, BTech building FutmMinna, MSc Construction management ABU, Zaria

Project Location: Kaduna

Contract duration: 180 days

This thread is open to constructive criticism. Am geographically mobile and ready to avail my services and expertise to those who may need it. Am competent in the following areas

***General building and civil engineering Construction.
(residential, commercial, industrial)
***drainage and culvert and mini bridge constructions
***road maintenance % new constructions
***surveying, valuation of work and prep of estimates
*** design and general consultancy

Pls avoid quoting whole write ups while asking questions or commenting. Once more. Make ur criticism constructive and professionally

Leggo guys

Whatsapp +234-813-110-9592
mozel247: 2:48am On Jun 08, 2019
The third structure is at roofing beam level while the remaining 5 at lintel level. We will be taking a short break while we expect next trench of fund.

While the wait lingers, am please to announce the starting of another project. Mami market to be handled by urs sincerely. Wish me well guys.

Link to thread will be posted shortly

mozel247: 10:15pm On May 30, 2019
Update.

Final block and concrete work on block one on course. Everything moving fine and we are on week 6 work actually commenced.

mozel247: 6:40am On May 26, 2019
Update

Four of the structures are at roof lintel level while the oversite concrete for the remaining 4 is on course once we get delivery of the next ruck of cement.

Electrical first fix commenced, woodwork for lintel and the casting of first lintel commenced. AC pipping also.

Digging of soakaway also. Pictures attached

mozel247: 1:46pm On May 22, 2019
Update


The four unit we casted the oversite concrete are almost at the lintel level completely. Don't let the pictures confuse u. This is not a duplex but a but just two bedroom flat bongalow. I love reinforcing my work well. Cutting corners is not always my thing. This is the area I do have issues with some of my clients. For me, professional excellence first before anything. Pictures attached

mozel247: 4:22am On May 21, 2019
Update

We proceeded with casting of the oversite concrete on a site abridged mix of 1:4:4. We are casting 4 first and then the remainder latter dates after raising the blocks

mozel247: 4:20am On May 21, 2019
UPDATE

Next we proceeded with dpc construction. I often use felt for my blockline and nylon everywhere. I often use non recycled nylon more expensive and hardly tear. I always spread sharp sand on it to hold it in position and make sure the stones are nearly arranged without damaging the felt or nylon.

Pics attached